Approval Process
Orange Island’s streamlined approval process ensures transparency, accountability, and efficient decision-making, guiding every request through the appropriate review channels for timely and compliant outcomes.
Requirements for Construction on Orange Island
STAGES
OIDC
SUBSCRIBERS
PRE-CONSTRUCTION PERMIT
- Send development fees
- Send OI development guidance manual
- Send OI rules and regulations
- Send Orange Island safety health environment and quality (sheq) policy
- Send OI preconstruction permit
- Pay development fees
- Acknowledge OI development guidance manual
- Acknowledge OI rules and regulations
- Acknowledge OI safety health environment and quality (sheq) policy
- Acknowledge OI fence concept design
- Receive preconstruction permit
CONSTRUCTION PERMIT
- Review all documents.
- Approve and prepare construction permit
- Organize a mandatory induction exercise in site office
- Issue construction permit
- Conduct routine inspections to ensure all compliance has been met.
- Soft / Hard copy of Lagos State Government (LASPPA & LABSCA)
- Evidence of building insurance
Endorsed OIMC / Approved Copy of:
- Architectural Drawings
- Structural Drawings
- Electrical Design
- Mechanical Design
- Soil Test /Geotechnical Report
- Structural Drawings with Calculation Sheets.
Endorsed by a COREN Certified Engr :
- A Copy of structural indemnity letter.
- Safety Commission Clearance (lasg)
- Evidence of Application from Lagos State Material Testing (LSMTL).
- Contractors Third Party Insurance Package
- A Copy of Contractors Construction Method statement.
- Evidence of Installation of Project Signage on site
- Availability of Functional /Installed Mobile Toilet on site
POST-CONSTRUCTION
- Inspection of OI infrastructures
- Receive a copy of certificate of fitness for habitation.
- Connect to OI facilities (Power, water, sewage) upon confirmation of compliance.
- Refund of caution fees (upon confirmation of no default)
- Submit certificate of fitness for habitation from LASG.